Description

This procedure concerns the granting of an establishment licence for a dedicated or mixed CNG/CBG/BioCNG filling station for public use to natural or legal persons, for the purpose of carrying out construction works.

At a glance

Points of ServicePoints of Single Contact (ΚΕΠ – EKE), Regional units, At the Directorate of Transport & Communications of the relevant Regional Unit.
Number of Documents0
CostVariable
Deadline of Implementation30 days
Process Diagram

Conditions

In order for an establishment licence to be granted, the terms, conditions, technical specifications, and the issuance procedure stipulated in Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402) must be met.

An application must have been submitted to the competent road authority for approval to lower the sidewalk curb (curb cut) or to establish a traffic connection, as the case may be.

The minimum safety distances for dedicated or mixed CNG/CBG/BioCNG filling stations must be observed (Article 5 of JMD no. 11709/15-01-2024).

Regarding the spatial siting, traffic connection (for areas outside the city plan), or curb cut/lowering of the sidewalk level (for areas within the city plan)—as applicable—for dedicated or mixed CNG/CBG/BioCNG filling stations undergoing the licensing process, the diagrams provided in Presidential Decree 1224/1981 (Government Gazette, Series A, No. 303) or Royal Decree 465/1970 (Government Gazette, Series A, No. 150) shall apply, as amended and currently in force.

In order to be granted a licence for the establishment of a filling station, natural persons—or members of companies—must be either Greek nationals or citizens of a Member State of the European Union or the European Economic Area (EEA). By way of exception, the granting of a licence to establish a liquid fuel filling station is permitted for ethnic Greeks (*omogeneis*) from Russia, Northern Epirus, Turkey, and Egypt, as well as for the children of such individuals. <br /><br /> For *sociétés anonymes* (public limited companies) with their registered office in the country, the nationality of the shareholders is not taken into consideration (paragraph 4 of Article 185, Law 4070/2012).

The legal entity must have its registered office in Greece.

The interested party (the natural person, or—in the case of a legal entity—its members and its representative) must have reached the age of majority, in accordance with electoral legislation.

The interested party—whether a natural person or a legal entity—must possess the right to use and exploit the plot of land or site for the purpose of establishing a fuel station.

In the case of a natural person, the interested party must not have been subject to a final conviction for fuel adulteration within the last eight years, nor to a first-instance conviction for fuel smuggling, subject to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183). <br /><br /> In the case of a legal entity: The legal representative must not have been subject to a final conviction, and the legal entity they represent must not have been held civilly liable (by a final judgment) for fuel adulteration within the last eight years. Furthermore, the legal representative must not have been subject to a first-instance conviction, and the legal entity they represent must not have been held civilly liable (by a first-instance judgment) for fuel smuggling, subject to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183).

The location where the filling station is to be established must be in an area permitted by the land-use regulations and the building terms and restrictions in force for that area, and where such use/installation is not prohibited by the applicable land-use provisions.

The design of the filling station’s facilities and equipment must take into account the requirements of current legislation, as well as relevant national and European regulations and standards.

The facilities must be subject to the Standard Environmental Commitments.

Construction work must be completed within two years, in accordance with the provisions of the applicable regulatory framework. (The establishment licence is valid for a period of two (2) years and may be extended for an additional two (2) years, provided that a relevant application is submitted before the expiration of the deadline, accompanied by a solemn declaration from the supervising engineer stating that construction works have not been completed. <br /><br /> In exceptional cases, an additional extension of three (3) months may be granted following the expiration of the extension period for the completion of the works.

For the establishment and operation of a mixed CNG/CBG/BioCNG filling station—which includes any type of fuel in addition to CNG/CBG/BioCNG—the terms and conditions for the establishment and operation of a liquid fuel station or a dedicated liquefied petroleum gas (LPG) station shall also be examined, as applicable.

Fees / Imposts

  • Issuance of the licence: €30. Additionally, for each pump or dispenser beyond the first (1st): €30.
    Fee code
    8240
    Payment type
    Hellenic PostBank cashierDigital (debit / credit card)Digital (web banking)
    Type
    e-Administrative Fee (variable)

What you will need

Identification and signature verification means
Identification document
  • Application for the issuance of an establishment licence for a dedicated or mixed CNG/CBG/BioCNG filling station for public use.
    Filed by
    Submitted by the applicant (exclusively in person)
    Note
    The application is submitted by the applicant (a natural or legal person). Otherwise, documents evidencing the authorization of the representative must be submitted along with the application. <br /><br /> In the event that the applicant is a legal person, the application—accompanied by the relevant supporting documentation—must be submitted by its legal representative. The application is submitted by the applicant to the competent Directorate of Transport and Communications of the relevant Regional Unit. <br /><br /> Alternatively, the interested party may submit the application, along with the required supporting documents, to a Citizen Service Centre (KEP-EKE); the latter shall then forward the application and the relevant file to the competent Directorate of Transport and Communications of the relevant Regional Unit.
    Applicant status
    Legal entities, Persons
Issuance of an establishment licence for a dedicated or mixed CNG/CBG/BioCNG filling station
What you will need
1Residence permitStay Permit
Filed by
Presented by the applicant
Applicant status
Persons
Notes
Ethnic Greeks from Turkey (*omogeneis*), upon submission of the required documentation, shall also present their valid residence document issued by the Aliens Centre, provided that the registration number of said document is recorded on the application.
2A topographical plan of the area (one copy), in accordance with paragraph 1(b) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402). It must be signed by the competent engineer, drawn to a scale of 1:200 or 1:500, and cover a radius of fifty (50) meters from the boundaries of the plot or land parcel; the coordinates of the site must be referenced to the National Geodetic Reference System (EGSA 87).Topographical drawing
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
The diagram shall indicate the plot or land parcel intended for the proposed dedicated or mixed CNG/CBG/BioCNG filling station, the dimensions of its boundaries, its location in relation to road widths, and the positioning of the building, tanks or cylinders, pumps and dispensers, and the tank or cylinder filling point, as well as the types of neighboring structures. Specifically, the diagram must indicate the locations of the key components of the proposed dedicated or mixed CNG/CBG/BioCNG filling station, along with all safety distances required under Article 5 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402). <br /><br /> The drawings and technical reports must be signed by the competent engineer and include a legend detailing the project, the applicant, and the designer, as well as a section outlining the technical specifications of the construction. The drawings and technical reports shall also be submitted in electronic format (PDF files) on a portable storage device (USB flash drive).
3Opinion from the Competent Authority, in accordance with paragraph 1(b) of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402).Advisory
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
If the dedicated or mixed filling station is located in the vicinity of areas subject to special protective provisions for the environment, as well as for cultural and natural heritage (archaeological sites/monuments, Natura 2000 sites, etc.), the opinion of the competent authority is required.
4A solemn declaration by the applicant, pursuant to Article 8 of Law 1599/1986, confirming the absence of a criminal conviction and the legal right to use and operate the plot of land, in accordance with point (c) of paragraph 1, Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024.Solemn Declaration
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
Specifically: a) In the event that the applicant is a natural person, they must solemnly declare that: i) within the last eight years, they have not been subject to a final (irrevocable) conviction for fuel adulteration, nor to a first-instance conviction for fuel smuggling, without prejudice to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183). <br /><br /> ii) they possess the legal right to use and operate the plot of land or site for the establishment of the dedicated or mixed CNG/CBG/BioCNG filling station. b) In the event that the applicant is a legal entity, its legal representative shall provide a solemn declaration stating that: <br /><br /> i) within the last eight years, neither the representative personally nor the legal entity they represent has been subject to a final conviction or a final judgment of civil joint liability for fuel adulteration; furthermore, neither the representative personally nor the legal entity they represent has been subject to a first-instance conviction or a first-instance judgment of civil joint liability for fuel smuggling—without prejudice to the provisions of Law 4177/2013 (Government Gazette, Series A, No. 183). <br /><br /> ii) the legal entity holds the legal right to use and operate the plot of land or site for the establishment of a dedicated or mixed CNG/CBG/BioCNG filling station.
5Solemn declaration (pursuant to Law 1599/86) by the engineer responsible for the design of the facility, in accordance with point (d) of paragraph 1, Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024.Solemn Declaration
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
A solemn declaration, pursuant to Article 8 of Law 1599/1986, by the engineer responsible for the design of the installation, stating the following: i) The location where the filling station is to be established lies within an area where such use is not prohibited by the applicable land-use regulations. ii) The terms and conditions of Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402) are met for a dedicated CNG/CBG/BioCNG filling station; in the case of a mixed filling station, the terms and conditions of Presidential Decree 1224/1981, Royal Decree 465/1970, and/or Presidential Decree 595/1984—as currently in force, depending on the specific fuel type—are also met. iii) The requirements of relevant national and European standards and regulations have been taken into account in the design of the installations and the equipment to be installed at the dedicated or mixed CNG/CBG/BioCNG filling station under development. iv) An application bearing reference no. ... has been submitted to the competent authority responsible for the maintenance and operation of the road(s) situated in front of the dedicated or mixed CNG/CBG/BioCNG filling station; the application meets all the requirements for the granting of approval for the lowering of the sidewalk curb, approval for an entrance/exit, or approval for a traffic connection, as the case may be.
6A plan, in one (1) copy, at a scale of 1:200, in accordance with paragraph 1(e) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402).Drawings / studies by an engineer / architect
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
The plan, at a scale of 1:200, shall show the location of the building and any auxiliary structures; the positioning of the CNG/CBG/BioCNG dispensing units to be installed, auxiliary equipment, and any portable CNG/CBG/BioCNG storage media (in the case of a "satellite" or "subsidiary" CNG/CBG/BioCNG station); the CNG/CBG/BioCNG tanks or cylinders; the "integrated unit"; the parking area for CNG/CBG/BioCNG tanker trucks; the flow-metering arrangement provided by the distribution company; the layout of the traffic connection or the curb cut/lowered sidewalk section(s) interfacing with the road(s); as well as the signage for the aforementioned elements. <br /><br /> The plans and technical reports must be submitted signed by the competent engineer and shall include a legend containing project details, information regarding the applicant and the designer, as well as a section detailing the technical specifications of the construction. The plans and technical reports shall also be provided in electronic format (as PDF files) on a portable storage device (USB flash drive).
7Electromechanical (E/M) installation plan, submitted in one (1) copy at an appropriate scale—depending on the size of the installation—accompanied by a file containing the Technical Specifications. This applies to installations located outside the buildings of a dedicated or mixed CNG/CBG/BioCNG filling station, in accordance with paragraph 1(f) of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024.Electromechanical drawing
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
The plan must clearly depict—in a distinct manner that demonstrates their harmonious coexistence and simultaneous proper operation—the following installations: * water supply and sewage networks * compressed air systems * any liquid fuel piping (in the case of a mixed filling station with liquid fuel facilities) * LPG supply piping (in the case of a mixed filling station with LPG facilities) * CNG/CBG/BioCNG piping * piping for filling storage vessels * tanks for liquid fuels, LPG, and CNG/CBG/BioCNG (in the case of a mixed filling station) * and the filling station’s electrical systems (power circuits, low-voltage/signal circuits, lighting, and grounding). Additionally, the plan must include the layout of the filling station’s explosion-proof (hazardous) zones. <br /> All plans and technical reports must be signed by the competent engineer and include a legend containing details regarding the project, the applicant, and the designer, as well as a section detailing the technical specifications of the construction. The plans and technical reports must also be submitted in electronic format (as PDF files) on a portable storage device (USB flash drive).
8Detailed drawings and technical specifications—in one (1) copy and at a scale of 1:50 or 1:20—of the facilities and equipment, in accordance with paragraph 1(ζ) of Article 12 of the Joint Ministerial Decision (JMD) no. 11709/15-01-2024.Drawings / studies by an engineer / architect
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
Specifically, the drawings must depict the following: aa) Floor plan and cross-section, showing all structures of the filling station (or combined filling station), their precise dimensions, as well as the construction specifications for walls, floors, ceilings, and any existing partitions required by the building permit. bb) Drawings of portable CNG/CBG/BioCNG storage units (in the case of a "subsidiary CNG/CBG/BioCNG filling station") and/or drawings of liquid fuel tanks, in accordance with the provisions of Article 17 of Presidential Decree 1224/1981 (Government Gazette, Series A, No. 303) and Royal Decree 465/1970 (Government Gazette, Series A, No. 150) (for cases involving a combined filling station with liquid fuel facilities), and/or LPG tanks, in accordance with the provisions of Article 25 of the Presidential Decree 595/1984 (Government Gazette, Series A, No. 218) (for the case of a mixed-use filling station that includes LPG installations). gg) Detailed drawings and specifications for other CNG/CBG/BioCNG installations—in the case of a dedicated CNG/CBG/BioCNG station, or a station combining liquid fuels and LPG—(such as air compressors, lifting equipment, automatic car wash systems, sludge/sediment traps, etc.), in accordance with the applicable provisions of Presidential Decree 1224/1981 (Government Gazette, Series A, No. 303), Royal Decree 465/1970 (Government Gazette, Series A, No. 150), and/or Presidential Decree 595/1984. <br /><br /> The drawings and technical reports must be submitted signed by the competent engineer and must include a legend containing information regarding the project, the applicant, and the designer, as well as a legend detailing the technical specifications of the construction. The drawings and technical reports must also be provided in electronic format (PDF files) on a portable storage device (USB flash drive).
9Technical report on the electromechanical (E/M) installations, signed by the competent engineer, detailing the overall structure of the installation, in accordance with paragraph 1 of Article 12 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024.Technical report
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
Technical report on the electromechanical installations (in one (1) copy), detailing the overall structure of the installation, the individual sub-installations, the equipment and machinery being installed, their technical specifications, their connection and operational methods, the national and European standards and regulations applied during their design and installation, and the study on the zoning of explosion-hazardous areas. <br /><br /> The plans and technical reports must be submitted signed by the competent engineer and must include a legend containing information about the project, the applicant, and the designer, as well as a legend detailing the technical specifications of the construction. <br /><br /> The plans and technical reports must also be provided in electronic format (PDF files) on a portable storage device (USB flash drive).
10Form for inclusion under Standard Environmental Commitments.Environmental Compliance Receipt
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
Form for adherence to standard environmental commitments, in accordance with the provisions of Joint Ministerial Decision (JMD) no. 46537/09-08-2013 (Official Gazette, Series B, 2036), as currently in force.
11Required studies and supporting documentation concerning the implementation of additional protective measures for the reduction of minimum safety distances, in accordance with Article 5 of Joint Ministerial Decision (JMD) no. 11709/15-01-2024.Technical study'
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entitiesPersons
Notes
The above items must be submitted in addition to any other required documentation, as stipulated by the applicable regulatory framework. Plans and technical reports must be signed by the competent engineer and include a legend containing details of the project, the applicant, and the designer, as well as a legend detailing the technical specifications of the construction. Plans and technical reports must also be provided in electronic format (PDF files) on a portable storage device (USB flash drive).
12Legal authorization documents for the legal representative.Legal documents from legal entities
Filed by
Submitted by the applicant (in person)
Applicant status
Legal entities
Notes
If the applicant is a legal entity, the articles of association (statutes) must be submitted, along with documentation regarding the appointment or authorization of the legal representative.

Legislation

  • Description
    Regarding the terms and conditions for the installation and operation of fuel pumps at filling stations located outside approved city or town plans—or, more generally, outside inhabited areas—and regarding the traffic connection of such facilities to public roads, as currently in force (as amended).
    Legal references
  • Description
    Regarding the terms and conditions for the establishment and operation of liquid fuel filling stations located within approved city or town plans, approved settlements, or, more generally, inhabited areas, as currently in force (as amended).
    Legal references
  • Description
    Amendment of Royal Decree 465/1970 "Regarding the terms and conditions for the installation and operation of fuel pumps at filling stations located outside approved city or town plans—or, more generally, outside inhabited areas—and regarding the traffic connection of such facilities to public roads" (Government Gazette, Series A, No. 150) and of Presidential Decree <br /><br /> 1224/1981 "Regarding the terms and conditions for the establishment and operation of liquid fuel filling stations located within approved city or town plans, approved settlements, or, more generally, inhabited areas" (Government Gazette, Series A, No. 303), as amended by Presidential Decree 509/1984 (Government Gazette, Series A, No. 181), Presidential Decree 143/1989 “Amendment of provisions regarding the terms and conditions for the installation and operation of fuel pumps and the traffic connection of facilities with roads” (Government Gazette, Series A, No. 69), Presidential Decree <br /><br /> 401/1993 (Government Gazette, Series A, No. 170) and Presidential Decree 125/1992 (Government Gazette, Series A, No. 56) “amendment and supplementation of Presidential Decree 143/89 (Government Gazette, Series A, No. 69)” and the repeal of provisions of Presidential Decree 327/1992 (Government Gazette, Series A, No. 163)," as amended and currently in force.
    Legal references
  • Description
    Incorporation into Greek legislation of Directive 2014/94/EU of the European Parliament and of the Council of 22 October 2014 on the deployment of alternative fuels infrastructure; simplification of the licensing procedure and other provisions regarding fuel and energy supply stations; and other provisions, as amended and currently in force.
    Legal references
  • Description
    Simplification and integration of the following procedures: * 1) Granting of establishment and operating licences of liquid fuel stations; * 2) Granting of establishment and operating licences of dedicated liquefied petroleum gas (LPG) stations; * 3) Granting of establishment and operating licences of compressed natural gas (CNG) distribution stations—falling under the remit of the Directorate for the Control of Vehicles and Facilities of the Ministry of Infrastructure, Transport and Networks—into the "Single Service Centres" (E.KE.) system, as amended and currently in force.
    Legal references
  • Description
    Amendment of Joint Ministerial Decision no. oik.81540/1445/Φ.4.2./31-12-2015 (Official Gazette, Series B, 2984), titled “Simplification and integration of the procedures for: * 1) Granting establishment and operating licences of liquid fuel filling stations. * 2) Granting establishment and operating licences of dedicated liquefied petroleum gas (LPG) filling stations. * 3) Granting establishment and operating licences of compressed natural gas (CNG) filling stations—falling under the remit of the Directorate for the Control of Vehicles and Facilities of the Ministry of Infrastructure, Transport and Networks—into the system of Single Service Centres (E.K.E.),” as currently amended and in force.
    Legal references
  • Description
    Procedures, technical specifications, and terms and conditions for the installation of monitoring and electronic data transmission systems for inputs and outputs, * a) at the facilities of operators of fuel and energy retail stations; * b) at the facilities of holders of a retail trade licence—specifically, sellers of heating oil; * c) at the facilities specified in cases (ζζ), (ηη), (θθ), (ιι), (ιαια), (ιβιβ), and (ιγιγ) of paragraph 7a of Article 31 of Law 3784/2009 (Government Gazette, Series A, No. 137). Compliance requirements, access to data by services, implementation timeline, transitional provisions, and any other necessary details regarding the safeguarding of data within the input-output monitoring system," as amended and currently in force.
    Legal references
  • Description
    Establishment of Standard Environmental Commitments for Category B activities under Group 11, "Refilling stations for vehicles using gaseous or liquid fuels"—falling within the subgroup "transport and handling of fuels and chemical substances"—as currently in force.
    Legal references
  • Description
    Regulations concerning matters under the jurisdiction of the Ministry of Transport and Communications, along with other provisions, as currently in force.
    Legal references
  • Description
    Establishment of a National Road Safety Council and a General Directorate for Road Safety; supervision and enhancement of the vehicle technical inspection system to promote road safety and environmental protection; ratification of an agreement between the Hellenic State and OASTH (Thessaloniki Urban Transport Organisation); and other provisions, as currently in force.
    Legal references
  • Description
    Amendment of Joint Decision A.1176/5-12-2024 regarding “Procedures, technical specifications and terms and conditions for the installation of monitoring and electronic transmission systems for input-output data: * (a) at the facilities of operators of fuel and energy supply stations * b) the facilities of holders of a retail trade licence—specifically sellers of heating oil; * c) the facilities specified in cases (zz), (hh), (thth), (ii), (iaia), (ibib), and (igig) of paragraph 7a of Article 31 of Law 3784/2009 (Government Gazette, Series A, No. 137). compliance requirements, access to data by the relevant authorities, the implementation timeline, transitional provisions, and any other necessary details regarding the safeguarding of data within the input-output monitoring system” (Government Gazette, Series B, No. 6827).
    Legal references
  • Description
    Determination of technical specifications, competent authorities, and the terms and conditions for the establishment and operation of filling stations equipped with dispensing devices (refuelling points) for compressed natural gas (CNG), compressed biomethane, and a compressed mixture of natural gas and biomethane for motor vehicles, namely: * 1. stations exclusively for compressed natural gas (CNG), or * 2. mixed filling stations comprising a. liquid fuels, liquefied petroleum gas (LPG), and compressed natural gas (CNG), or b. liquefied petroleum gas (LPG) and compressed natural gas (CNG), or c. liquid fuels and compressed natural gas (CNG).
    Legal references
  • Description
    Terms and conditions for the installation and operation of LPG filling stations, as currently in force (as amended).
    Legal references

About

Process code
238664
NACE code
47.3
Description of NACE code
Retail sale of automotive fuel in specialised stores
Legal means of protection or appeal
Administrative appeal, Other Administrative Appeal

Provision is made for a request for administrative review (*aitisi therapeias*) to be submitted to the authority that issued the act, or for a special administrative appeal to be filed with the Coordinator of the Decentralized Administration within a 15-day deadline, in accordance with the provisions of Articles 227 and 228 of Law 3852/2010 (Government Gazette, Series A, No. 87), as amended by Law 4555/2018 (Government Gazette, Series A, No. 133) and currently in force.

Other Information

Remarks

Joint Ministerial Decision (JMD) no. 11709/15-01-2024 (Government Gazette, Series B, No. 402) defines the terms, conditions, technical specifications, and the procedure for issuing establishment and operating licences for the installation and operation of dedicated or mixed filling stations—designed for the storage and distribution of compressed natural gas, biomethane, or a mixture of natural gas and biomethane (CNG/CBG/BioCNG)—for use by motor vehicles, whether for public or private use. Depending on the categories of fuel handled, a "CNG/CBG/BioCNG filling station" is classified as follows: i) A "dedicated CNG/CBG/BioCNG filling station"—whether for public or private use—which supplies motor vehicles exclusively with CNG/CBG/BioCNG. ii) A "mixed CNG/CBG/BioCNG filling station"—whether for public or private use—which supplies motor vehicles with CNG/CBG/BioCNG, liquid fuels (gasoline/diesel), and/or liquefied petroleum gas (LPG) (the latter only in the case of a public station), in any combination thereof. <br /><br /> The establishment licence is granted within thirty (30) working days, provided that the legal requirements are met. In the event that supporting documentation is resubmitted, the licence is granted within fifteen (15) working days, provided that the legal requirements are met. <br /><br /> For the purpose of carrying out construction work, the establishment licence is valid for a period of two (2) years; it may be extended for an additional two (2) years, provided that a relevant application is submitted prior to the expiration of the initial term, accompanied by a solemn declaration from the supervising engineer stating that the construction work has not yet been completed. In exceptional cases, an additional extension of three (3) months may be granted following the expiration of the extension period for the completion of the works. <br /><br /> Upon completion of the construction works, the establishment licence remains valid indefinitely, serving as the legal title for the existing facilities.

ID: 238664

Name: Issuance of an establishment licence for a dedicated or mixed CNG/CBG/BioCNG filling station